Water Line Work on Torre Avenue and Pacifica Drive

Published on April 17, 2025

Water Line Work Image.png

The City of Cupertino is moving forward with important infrastructure upgrades as part of the Torre Avenue and Pacifica Drive Water Main Replacement Project. This project is designed to replace aging water infrastructure, ensuring improved water service reliability for residents and businesses in the area.

Construction began this week, with different phases scheduled over the coming months:

Torre Avenue

  • April 7–16: Potholing and saw cutting for utility verification and preparation (eight working days)
  • April 23–May 9: Installation of a new 12” water main and related services (13 working days)
  • May 22–June 13: Final service tie-ins and pavement restoration (16 working days)

Pacifica Drive

  • April 8–22: Saw cutting and installation of a new 12” water main (10 working days)
  • May 12–30: Final connections for domestic water, hydrants, fire services, and irrigation (13 working days)
  • June 2–13: Pavement restoration (10 working days)

All construction will occur Monday through Friday from 8:30 a.m. to 2:30 p.m., excluding holidays and major City events.

What to Expect

  • Traffic and Parking Impacts: Parking along Torre Avenue will be limited during construction. Traffic control measures may also cause delays, so drivers are encouraged to plan ahead.
  • Service Notifications: Any planned water service shutoffs will be communicated in advance, with at least 72 hours' notice given to City Hall and the Cupertino Library.

For more information, contact Public Works at 408-777-3354.

 